Status

Status

brigade-woods-project-status

A Block : Above Terrace floor LMR top slab concreting completed. 4th floor block work completed. 3rd floor plastering works in progress. Ground floor PHE pipeline works in progress - September 2020

brigade-woods-project-status

B Block : 3rd floor slab concreting completed. Ground floor block work completed - September 2020

brigade-woods-project-status

C Block : Ground floor slab shuttering works in progress - September 2020

brigade-woods-project-status

D Block : Ground floor slab concreting completed - September 2020

brigade-woods-project-status

E Block : OHT wall reinforcement works in progress. 3rd floor plastering works in progress. Balcony railing works in progress - September 2020

brigade-woods-project-status

F Block : LMR top slab concreting completed. 3rd floor plastering works in progress. Balcony railing works in progress - September 2020

brigade-woods-project-status

G Block : Above Terrace floor-SHR & LMR bottom slab concreting completed. 3rd floor block work in progress - September 2020

brigade-woods-project-status

H Block : Above terrace floor column shuttering works in progress - September 2020

brigade-woods-project-status

J Block : Above terrace floor, column concreting works in progress. Balcony railing works in progress. External plastering works in progress - September 2020

brigade-woods-project-status

K Block : LMR block work in progress. 1st floor kitchen and toilet dado works are in progress. 1st floor IPS flooring in progress - September 2020

brigade-woods-project-status

L Block : OHT wall concreting works in progress - September 2020

brigade-woods-project-status

M Block : 3rd floor slab concreting completed. Ground block work in progress - September 2020

brigade-woods-project-status

N Block : 3rd floor slab shuttering work in progress. Ground floor block work in progress. Stilt floor VDF in progress - September 2020

brigade-woods-project-status

P Block : 3rd floor beam reinforcement works in progress. Ground floor block work in progress - September 2020

brigade-woods-project-status

Q Block : 2nd floor water proofing works in progress. 3rd floor internal plastering works in progress - September 2020

brigade-woods-project-status

R Block : Ground floor concealed piping and high level works in progress. Up to 4th floor internal wall plastering works completed - September 2020

brigade-woods-project-status

S Block : 1st floor slab concreting completed - September 2020

brigade-woods-project-status

Club House : Ground floor slab shuttering works in progress - September 2020

Speak to usclose-button

Please select your country and enter your phone number

I Agree to the Terms & Conditions

Thank you for requesting a call back
Our team will get back to you shortly!