Block K – First floor slab shuttering & electrical conduiting in progress - May 2019

Block L – First Floor slab shuttering in progress - May 2019

Block G & J – First Floor slab shuttering in progress - May 2019

Block Q - First Floor slab shuttering in progress - May 2019

R Block – Columns to first floor in progress - May 2019

A Block – Columns to first floor in progress - May 2019

Block H – Ground floor slab completed. Columns to first floor in progress - May 2019

Block E & F - Ground Floor slab shuttering in progress - May 2019

Block M - Upper Basement (Stilt) floor slab completed. Stilt to ground floor columns in progress - May 2019

Block P – Ground floor floor slab shuttering in progress - May 2019

Block N – Upper Basement (Stilt) floor slab shuttering in progress - May 2019

B Block - Upper Basement (Stilt) floor slab shuttering in progress - May 2019

C & D Blocks – Foundation and retaining wall works in progress - May 2019

STP–Platform works completed, columns to upper basement floor in progress - May 2019