Status

Status

brigade-woods-project-status

A Block : Wooden Door fixing in progress. Window grill installation completed. Internal Putty Works in progress. UPVC Windows & Doors installation in progress - June 2021

brigade-woods-project-status

A Block : Wooden Door fixing in progress. Window grill installation completed. Internal Putty Works in progress. UPVC Windows & Doors installation in progress - June 2021

brigade-woods-project-status

A Block : Wooden Door fixing in progress. Window grill installation completed. Internal Putty Works in progress. UPVC Windows & Doors installation in progress - June 2021

brigade-woods-project-status

B Block : Toilet dado & Flooring works in progress. Internal Putty works in progress - June 2021

brigade-woods-project-status

B Block : Toilet dado & Flooring works in progress. Internal Putty works in progress - June 2021

brigade-woods-project-status

C Block : 4th floor block work in progress. Ground floor Internal Plastering in progress - June 2021

brigade-woods-project-status

C Block : 4th floor block work in progress. Ground floor Internal Plastering in progress - June 2021

brigade-woods-project-status

D Block : South Elevation Pergola works in progress - June 2021

brigade-woods-project-status

E Block : North & South elevation external painting works in progress - June 2021

brigade-woods-project-status

E Block : North & South elevation external painting works in progress - June 2021

brigade-woods-project-status

F Block : North & South elevation external painting works in progress. Wooden Door fixing. UPVC Windows fixing in progress - June 2021

brigade-woods-project-status

F Block : North & South elevation external painting works in progress. Wooden Door fixing. UPVC Windows fixing in progress - June 2021

brigade-woods-project-status

G Block : South elevation balcony railing painting works commenced. UPVC window installation works in progress - June 2021

brigade-woods-project-status

H Block : Lift granite cladding works in progress. Internal Putty Work in progress. Staircase Jally works in progress - June 2021

brigade-woods-project-status

H Block : Lift granite cladding works in progress. Internal Putty Work in progress. Staircase Jally works in progress - June 2021

brigade-woods-project-status

J Block : Lift Granite cladding works in progress UPVC window installation works in progress. Wooden Door fixing in progress. Window grill installation works in progress - June 2021

brigade-woods-project-status

J Block : Lift Granite cladding works in progress UPVC window installation works in progress. Wooden Door fixing in progress. Window grill installation works in progress - June 2021

brigade-woods-project-status

J Block : Lift Granite cladding works in progress UPVC window installation works in progress. Wooden Door fixing in progress. Window grill installation works in progress - June 2021

brigade-woods-project-status

K Block : Terrace Plumbing Works in progress. Staircase flooring works in progress. Painting Works in progress. Wooden flooring works in progress - June 2021

brigade-woods-project-status

K Block : Terrace Plumbing Works in progress. Staircase flooring works in progress. Painting Works in progress. Wooden flooring works in progress - June 2021

brigade-woods-project-status

K Block : Terrace Plumbing Works in progress. Staircase flooring works in progress. Painting Works in progress. Wooden flooring works in progress - June 2021

brigade-woods-project-status

L Block : UPVC window installation works in progress. Wooden door fixing in progress. Internal Putty works in progress - June 2021

brigade-woods-project-status

L Block : UPVC window installation works in progress. Wooden door fixing in progress. Internal Putty works in progress - June 2021

brigade-woods-project-status

M Block : South Elevation External Texture in progress. Staircase Plastering in progress - June 2021

brigade-woods-project-status

M Block : South Elevation External Texture in progress. Staircase Plastering in progress - June 2021

brigade-woods-project-status

N Block : Toilet dado works in progress. Lift erection/installation works in progress. Bedroom Wooden flooring screed works completed upto 1st floor. South elevation External Plastering works in progress - June 2021

brigade-woods-project-status

N Block : Toilet dado works in progress. Lift erection/installation works in progress. Bedroom Wooden flooring screed works completed upto 1st floor. South elevation External Plastering works in progress - June 2021

brigade-woods-project-status

N Block : Toilet dado works in progress. Lift erection/installation works in progress. Bedroom Wooden flooring screed works completed upto 1st floor. South elevation External Plastering works in progress - June 2021

brigade-woods-project-status

P Block : Internal plastering works – 3rd floor in progress. Balcony railing works in progress. Internal Putty Works in progress - June 2021

brigade-woods-project-status

P Block : Internal plastering works – 3rd floor in progress. Balcony railing works in progress. Internal Putty Works in progress - June 2021

brigade-woods-project-status

Q Block : North Elevation External texture completed. South Elevation External Plastering Work in progress - June 2021

brigade-woods-project-status

Q Block : North Elevation External texture completed. South Elevation External Plastering Work in progress - June 2021

brigade-woods-project-status

R Block : Wooden Doors fixing works in progress. Lift installation works completed. UPVC Window fixing works in progress - June 2021

brigade-woods-project-status

R Block : Wooden Doors fixing works in progress. Lift installation works completed. UPVC Window fixing works in progress - June 2021

brigade-woods-project-status

R Block : Wooden Doors fixing works in progress. Lift installation works completed. UPVC Window fixing works in progress - June 2021

brigade-woods-project-status

S Block : 4th floor Internal Plastering works in progress. North Elevation External plastering in progress - June 2021

brigade-woods-project-status

S Block : 4th floor Internal Plastering works in progress. North Elevation External plastering in progress - June 2021

brigade-woods-project-status

Club House : 1st & 2nd floor Internal Plastering work in progress. North & East Elevation Plastering works in progress - June 2021

brigade-woods-project-status

Club House : 1st & 2nd floor Internal Plastering work in progress. North & East Elevation Plastering works in progress - June 2021

brigade-woods-project-status

External development : Central Courtyard. North side road formation and planter box works in progress. Ramp between A and R blocks Planter works in progress - June 2021

brigade-woods-project-status

External development : Central Courtyard. North side road formation and planter box works in progress. Ramp between A and R blocks Planter works in progress - June 2021

brigade-woods-project-status

External development : Central Courtyard. North side road formation and planter box works in progress. Ramp between A and R blocks Planter works in progress - June 2021

brigade-woods-project-status

External development : Central Courtyard. North side road formation and planter box works in progress. Ramp between A and R blocks Planter works in progress - June 2021

brigade-woods-project-status

A Block : “On Installation of lifts” milestone - 30th June 2021

brigade-woods-project-status

Q Block : “On Installation of lifts” milestone - 30th June 2021

brigade-woods-project-status

J Block : “On Installation of lifts” milestone - 30th June 2021

brigade-woods-project-status

G Block : “On Installation of lifts” milestone - 30th June 2021

brigade-woods-project-status

R Block : “On Installation of lifts” milestone - 30th June 2021

brigade-woods-project-status

E Block : “On Installation of lifts” milestone - 15th June 2021

brigade-woods-project-status

F Block : “On Installation of lifts” milestone - 15th June 2021

brigade-woods-project-status

H Block : “On Installation of lifts” milestone - 15th June 2021

brigade-woods-project-status

K Block : “On Installation of lifts” milestone - 15th June 2021

brigade-woods-project-status

L Block : “On Installation of lifts” milestone - 15th June 2021

Speak to usclose-button

Please select your country and enter your phone number

I Agree to the Terms & Conditions

Thank you for requesting a call back
Our team will get back to you shortly!