Status
Status
A Block : Terrace flooring work in progress. 1st floor Lobby, Lift cladding work in progress. South elevation external texture works in progress. 3rd and 4th floor (Flat series 02 & 03) - Tile flooring works in progress - March 2021
A Block : Terrace flooring work in progress. 1st floor Lobby, Lift cladding work in progress. South elevation external texture works in progress. 3rd and 4th floor (Flat series 02 & 03) - Tile flooring works in progress - March 2021
A Block : Terrace flooring work in progress. 1st floor Lobby, Lift cladding work in progress. South elevation external texture works in progress. 3rd and 4th floor (Flat series 02 & 03) - Tile flooring works in progress - March 2021
B Block : Terrace floor waterproofing works in progress. Lift Machine Room plaster work completed. Up to 3rd floor toilet, kitchen utility waterproofing and screed work in progress. South elevation external plastering work in progress - Tile flooring works in progress - March 2021
B Block : Terrace floor waterproofing works in progress. Lift Machine Room plaster work completed. Up to 3rd floor toilet, kitchen utility waterproofing and screed work in progress. South elevation external plastering work in progress - Tile flooring works in progress - March 2021
C Block : Terrace floor slab shuttering work in progress. 3rd floor block work in progress - March 2021
D Block : LMR and SHR column works in progress. 3rd floor block work in progress. 1st floor internal plastering work in progress - March 2021
D Block : LMR and SHR column works in progress. 3rd floor block work in progress. 1st floor internal plastering work in progress - March 2021
E Block : Terrace floor waterproofing work completed. OHT waterproofing works in progress - March 2021
F Block : Terrace flooring works in progress. 2nd floor Balcony flooring works in progress - March 2021
G Block : 3rd floor tile flooring work in progress. Up to 1st floor IPS flooring works in progress - March 2021
H Block : Toilet ceiling primer works in progress. LMR plaster work completed. Lift installation works-scaffolding erection completed. Up to 4th floor internal flat 2nd coat putty works completed - March 2021
J Block : North and South Elevation external texture works completed. LMR external plaster work completed - March 2021
K Block : 1st to 4th floor Balcony flooring works in progress. 1st to 4th floor Window grill works in progress. 1st to 4th floor UPVC sliding door fixing in progress. 1st and 2nd floor Door fixing in progress - March 2021
K Block : 1st to 4th floor Balcony flooring works in progress. 1st to 4th floor Window grill works in progress. 1st to 4th floor UPVC sliding door fixing in progress. 1st and 2nd floor Door fixing in progress - March 2021
K Block : 1st to 4th floor Balcony flooring works in progress. 1st to 4th floor Window grill works in progress. 1st to 4th floor UPVC sliding door fixing in progress. 1st and 2nd floor Door fixing in progress - March 2021
L Block : LMR external plaster work completed. Terrace flooring works in progress - March 2021
M Block : North elevation external plaster work commencement. LMR & OHT top slab top slab concreting work completed. LMR block work completed - March 2021
M Block : North elevation external plaster work commencement. LMR & OHT top slab top slab concreting work completed. Up to 3rd floor internal plastering work completed. Terrace waterproofing work commenced - March 2021
M Block : North elevation external plaster work commencement.Terrace waterproofing work commenced. Up to 3rd floor toilet, kitchen utility waterproofing and screed works in progress. Terrace floor waterproofing coating works in progress - March 2021
N Block : Up to 3rd floor internal plastering work completed. LMR and OHT top slab concreting work completed. Up to 3rd floor toilet, kitchen utility waterproofing and screed works in progress - March 2021
P Block : Up to 1st floor lobby plastering work in progress. North elevation balcony railing works in progress. SHR and LMR top slab concreting work completed. Up to 1st floor, toilet waterproofing and screed work completed - March 2021
P Block : Up to 1st floor lobby plastering work in progress. North elevation balcony railing works in progress. SHR and LMR top slab concreting work completed. Up to 1st floor, toilet waterproofing and screed work completed - March 2021
Q Block : North elevation external texture and pergola works in progress. LMR plastering work completed. South elevation external plastering work in progress. Terrace floor waterproofing coating and membrane works in progress - March 2021
Q Block : North elevation external texture and pergola works in progress. LMR plastering work completed. South elevation external plastering work in progress. Terrace floor waterproofing coating and membrane works in progress - March 2021
R Block : South elevation texture work in progress. 3rd and 4th floor tile flooring work in progress. Lift Machine Room block work in progress. Terrace floor waterproofing coating works in progress. SHR plastering work completed - March 2021
S Block : Up to 1st floor toilet, kitchen utility waterproofing and screed works in progress. LMR and OHT top slab concreting work completed. 3rd floor internal plaster work in progress - March 2021
S Block : Up to 1st floor toilet, kitchen utility waterproofing and screed works in progress. LMR and OHT top slab concreting work completed. 3rd floor internal plaster work in progress - March 2021
Club House : Up to 1st floor block work in progress. Swimming pool slab concreting, work completed. Badminton court top slab shuttering and reinforcement works in progress - March 2021
Club House : Up to 1st floor block work in progress. Swimming pool slab concreting, work completed. Badminton court top slab shuttering and reinforcement works in progress - March 2021
External Development : STP waterproofing works in progress. North side compound wall-block work, plastering work, MS railing works in progress - March 2021
External Development : STP waterproofing works in progress. North side compound wall-block work, plastering work, MS railing works in progress - March 2021
© 2021 Brigade Enterprises LTD. All Rights Reserved.
Brigade Woods offers apartments for sale in Whitefield. Home to over 17 different species of flora, Brigade Woods is an exemplary project where nature and modern infrastructure entwine harmoniously. Brigade Woods is next to Brigade Tech Park and is surrounded by IT Parks, hospitals, banks, restaurants and reputed educational institutions. The location is known for its thriving social community and physical infrastructure. Brigade Woods offers 3 BHK apartments for sale in Whitefield, along with a range of world class amenities, and facilities that ensure the fulfillment of not just an individual’s needs, but also a family’s needs.
The world-class amenities available at Brigade Woods include a gym, a billiards room, a games room, a convenience store, a swimming pool, a tennis court, an open lawn, a jogging track, a reflexology track, and so much more. These amenities are not only fun to engage in, but also ensure fitness and general well-being. Brigade Woods is a strategically located establishment, and everything you will ever need is very close to you. No one must ever be worried about being too far from something. The most distinguishing feature of Brigade Woods apartments in Whitefield would be the open areas within the society, and just the fresh air all around the society.
Brigade Woods has nature written all over it, and it is just a very peaceful place to live in. Brigade Woods is a smart and strategic newly launched apartment in ITPL that caters to all you and your family’s needs. All of Brigade Woods’s features together make it one of the most desirable upcoming projects in Whitefield. You can book a visit today and check the place out for yourself. It is one of the most investable properties today, so book your dream apartment at Brigade Woods today.
Speak to us
Thank you for requesting a call back
Our team will get back to you shortly!