Status

Status

brigade-woods-project-status

A Block :North Elevation External texture work in progress.
Up to 1st floor Wooden flooring screed concrete (IPS) work completed.
Ground floor- Tile flooring works in progress. - December 2020

brigade-woods-project-status

B Block : SHR and LMR bottom slab concreting work completed.
North elevation external plastering work in progress.
4th floor block work in progress.
2nd floor internal plastering work in progress. - December 2020

brigade-woods-project-status

C Block : 1st to 2nd floor column works in progress. - December 2020

brigade-woods-project-status

D Block : 3rd floor slab concreting work completed. - December 2020

brigade-woods-project-status

E Block : North Elevation external texture and cladding work in progress.
South Elevation external plastering work in progress.
Up to 3rd floor internal plastering work completed. - December 2020

brigade-woods-project-status

F Block : North Elevation Texture work in progress.
South Elevation external plastering and balcony railing work in progress. - December 2020

brigade-woods-project-status

G Block : North Elevation external plastering work in progress.
South Elevation balcony railing work in progress. - December 2020

brigade-woods-project-status

H Block : East Elevation external plastering work in progress.
North elevation external texture work in progress. - December 2020

brigade-woods-project-status

J Block : South Elevation external plastering work in progress. - December 2020

brigade-woods-project-status

K Block : Lobby painting and flooring work in progress.Shaft piping works in progress. - December 2020

brigade-woods-project-status

K Block : LMR-Lift installation works in progress.South elevation external plastering work in progress. - December 2020

brigade-woods-project-status

L Block : LMR top slab and OHT works completed.Terrace floor waterproofing-screed work completed.Lift installation work in progress. - December 2020

brigade-woods-project-status

M Block : SHR and LMR bottom slab shuttering works in progress. 2nd floor block work completed. 1st floor internal plastering work in progress. - December 2020

brigade-woods-project-status

N Block : Terrace floor slab concreting work completed. 3rd floor block work in progress. Ground floor internal plastering work in progress. - December 2020

brigade-woods-project-status

P Block : Terrace floor slab shuttering works in progress. 2nd floor block work in progress.- December 2020

brigade-woods-project-status

Q Block : Ground floor toilet dado works in progress. Up to 4th floor putty works completed. - December 2020

brigade-woods-project-status

R Block : North and South elevation external texture work in progress. - December 2020

brigade-woods-project-status

S Block : 4th floor slab concreting work completed. - December 2020

brigade-woods-project-status

Club House : Above 2nd floor slab column reinforcement works in progress. - December 2020

brigade-woods-project-status

External Development : South and North side compound retaining wall works in progress. - December 2020

Speak to usclose-button

Please select your country and enter your phone number

I Agree to the Terms & Conditions

Thank you for requesting a call back
Our team will get back to you shortly!