Status

Status

brigade-woods-project-status

A Block : Terrace flooring work in progress. 1st floor Lobby, Lift cladding work in progress. South elevation external texture works in progress. 3rd and 4th floor (Flat series 02 & 03) - Tile flooring works in progress - March 2021

brigade-woods-project-status

A Block : Terrace flooring work in progress. 1st floor Lobby, Lift cladding work in progress. South elevation external texture works in progress. 3rd and 4th floor (Flat series 02 & 03) - Tile flooring works in progress - March 2021

brigade-woods-project-status

A Block : Terrace flooring work in progress. 1st floor Lobby, Lift cladding work in progress. South elevation external texture works in progress. 3rd and 4th floor (Flat series 02 & 03) - Tile flooring works in progress - March 2021

brigade-woods-project-status

B Block : Terrace floor waterproofing works in progress. Lift Machine Room plaster work completed. Up to 3rd floor toilet, kitchen utility waterproofing and screed work in progress. South elevation external plastering work in progress - Tile flooring works in progress - March 2021

brigade-woods-project-status

B Block : Terrace floor waterproofing works in progress. Lift Machine Room plaster work completed. Up to 3rd floor toilet, kitchen utility waterproofing and screed work in progress. South elevation external plastering work in progress - Tile flooring works in progress - March 2021

brigade-woods-project-status

C Block : Terrace floor slab shuttering work in progress. 3rd floor block work in progress - March 2021

brigade-woods-project-status

D Block : LMR and SHR column works in progress. 3rd floor block work in progress. 1st floor internal plastering work in progress - March 2021

brigade-woods-project-status

D Block : LMR and SHR column works in progress. 3rd floor block work in progress. 1st floor internal plastering work in progress - March 2021

brigade-woods-project-status

E Block : Terrace floor waterproofing work completed. OHT waterproofing works in progress - March 2021

brigade-woods-project-status

F Block : Terrace flooring works in progress. 2nd floor Balcony flooring works in progress - March 2021

brigade-woods-project-status

G Block : 3rd floor tile flooring work in progress. Up to 1st floor IPS flooring works in progress - March 2021

brigade-woods-project-status

H Block : Toilet ceiling primer works in progress. LMR plaster work completed. Lift installation works-scaffolding erection completed. Up to 4th floor internal flat 2nd coat putty works completed - March 2021

brigade-woods-project-status

J Block : North and South Elevation external texture works completed. LMR external plaster work completed - March 2021

brigade-woods-project-status

K Block : 1st to 4th floor Balcony flooring works in progress. 1st to 4th floor Window grill works in progress. 1st to 4th floor UPVC sliding door fixing in progress. 1st and 2nd floor Door fixing in progress - March 2021

brigade-woods-project-status

K Block : 1st to 4th floor Balcony flooring works in progress. 1st to 4th floor Window grill works in progress. 1st to 4th floor UPVC sliding door fixing in progress. 1st and 2nd floor Door fixing in progress - March 2021

brigade-woods-project-status

K Block : 1st to 4th floor Balcony flooring works in progress. 1st to 4th floor Window grill works in progress. 1st to 4th floor UPVC sliding door fixing in progress. 1st and 2nd floor Door fixing in progress - March 2021

brigade-woods-project-status

L Block : LMR external plaster work completed. Terrace flooring works in progress - March 2021

brigade-woods-project-status

M Block : North elevation external plaster work commencement. LMR & OHT top slab top slab concreting work completed. LMR block work completed - March 2021

brigade-woods-project-status

M Block : North elevation external plaster work commencement. LMR & OHT top slab top slab concreting work completed. Up to 3rd floor internal plastering work completed. Terrace waterproofing work commenced - March 2021

brigade-woods-project-status

M Block : North elevation external plaster work commencement.Terrace waterproofing work commenced. Up to 3rd floor toilet, kitchen utility waterproofing and screed works in progress. Terrace floor waterproofing coating works in progress - March 2021

brigade-woods-project-status

N Block : Up to 3rd floor internal plastering work completed. LMR and OHT top slab concreting work completed. Up to 3rd floor toilet, kitchen utility waterproofing and screed works in progress - March 2021

brigade-woods-project-status

P Block : Up to 1st floor lobby plastering work in progress. North elevation balcony railing works in progress. SHR and LMR top slab concreting work completed. Up to 1st floor, toilet waterproofing and screed work completed - March 2021

brigade-woods-project-status

P Block : Up to 1st floor lobby plastering work in progress. North elevation balcony railing works in progress. SHR and LMR top slab concreting work completed. Up to 1st floor, toilet waterproofing and screed work completed - March 2021

brigade-woods-project-status

Q Block : North elevation external texture and pergola works in progress. LMR plastering work completed. South elevation external plastering work in progress. Terrace floor waterproofing coating and membrane works in progress - March 2021

brigade-woods-project-status

Q Block : North elevation external texture and pergola works in progress. LMR plastering work completed. South elevation external plastering work in progress. Terrace floor waterproofing coating and membrane works in progress - March 2021

brigade-woods-project-status

R Block : South elevation texture work in progress. 3rd and 4th floor tile flooring work in progress. Lift Machine Room block work in progress. Terrace floor waterproofing coating works in progress. SHR plastering work completed - March 2021

brigade-woods-project-status

S Block : Up to 1st floor toilet, kitchen utility waterproofing and screed works in progress. LMR and OHT top slab concreting work completed. 3rd floor internal plaster work in progress - March 2021

brigade-woods-project-status

S Block : Up to 1st floor toilet, kitchen utility waterproofing and screed works in progress. LMR and OHT top slab concreting work completed. 3rd floor internal plaster work in progress - March 2021

brigade-woods-project-status

Club House : Up to 1st floor block work in progress. Swimming pool slab concreting, work completed. Badminton court top slab shuttering and reinforcement works in progress - March 2021

brigade-woods-project-status

Club House : Up to 1st floor block work in progress. Swimming pool slab concreting, work completed. Badminton court top slab shuttering and reinforcement works in progress - March 2021

brigade-woods-project-status

External Development : STP waterproofing works in progress. North side compound wall-block work, plastering work, MS railing works in progress - March 2021

brigade-woods-project-status

External Development : STP waterproofing works in progress. North side compound wall-block work, plastering work, MS railing works in progress - March 2021

Speak to usclose-button

Please select your country and enter your phone number

I Agree to the Terms & Conditions

Thank you for requesting a call back
Our team will get back to you shortly!